Wind Generation Appeal Update

    View Authors November 2015

    Please find attached our summary of wind generation appeal decisions issued between 12 October and 3 November 2015.

    Some facts for you in relation to the summary:

    • 19 decisions have been issued during this time, only 3 of which were allowed
    • 14 related to single turbine projects, 2 of which were allowed
    • 3 related to two turbine schemes, only one of which was allowed
    • 2 related to larger schemes, both of which were dismissed

    With regards to the English decisions, decisions have noted the WMS as a material consideration. As with the October update, there are a couple of decisions where the WMS has been used an absolute test, with any failure to meet the transitional provisions resulting in the appeals being dismissed.

    If you would like to discuss any of the decisions or any renewable energy projects that you are involved with, please do not hesitate to call me.